Standalone Public Plans

The Department of Inspections and Permits (I&P) has received numerous requests related to “standalone” public improvements and plan submittals. Currently, there is no published guidance regarding the review, permitting of these projects.

Standalone public plan submittals are generally  associated with projects where there is not a development plan or permit associated already in place or where these improvements themselves do not trigger a development plan or application. These standalone plans include projects, but not limited to, where the property has a failing septic system or failing well system and the site is proposing to tie to public infrastructure along their frontage.

The purpose of this memo is to provide guidance to all involved in the planning, permitting and construction of improvements related to standalone public improvements. This guidance does not cover all the scenarios where standalone improvements may apply;  nor does it speak to all situations where these improvements may trigger development approvals, permits.

This guidance is provided in the form of  Frequently Asked Questions (FAQ’s) on the County website that summarize permitting requirements involving standalone public improvements for residential and non-residential projects.

  • Standalone public improvements generally include projects where there is a failing septic system or failing well system and a connection to  public infrastructure along the property frontage is proposed.  
  • Projects where there is no other proposed property development  except connection to  public infrastructure (water, sewer) along the property frontage 
  • For improvements not associated with a development project and that involve grading, cut/fill (e.g., addition of a sidewalk section/new sidewalk  within a public rights-of-way, new storm drainage or stormwater conveyances) are reviewed on a case by case basis. Coordination, prior discussion with I&P engineering staff  is required regarding the permitting of these types of projects.
     
  • In general- Public plans are required when public improvements are proposed related to public storm drain, water and sewer, Stormwater management plans, and road plans.
  • For standalone improvements - Public plans are required when public improvements are proposed due to a failing septic system or failing well system, and the connection cannot be completed with a TAP permit. 
     
  • For these types of projects, it is recommended to set-up a presubmittal meeting. Contact ipengineering@aacounty.org to set-up a pre-submittal meeting prior to the submission.
  • If the project needs a sewer study, this would be required before public plan submission
  • The submittal along with a cover letter, completed checklists (water, sewer, roads, etc.)  is required and should be emailed to ipengineering@aacounty.org   
  • A cover letter to explain the reason to request connection for public infrastructure shall  be included in the package.

  • If the property use is Non-Residential: 
    • Submit public plans, cost estimates (unless using TAP permit  - see #8 for tap permit requirements). Note that when extension of water/sewer/ is proposed a TAP permit may not be used or when an easement is required for the public infrastructure.
    • Submit an Onsite Permit using LUN 
    • Clearly state in the detailed description- Connection to public water or public sewer due to failed septic/well system 
    • The assigned engineering reviewer will determine if a Public Works Agreement or TAP permit is required

  • EDU Worksheets are required for all commercial projects https://aacoprod.aacounty.org/EDU/returnEDUWorksheet.do  
  • A fire flow test is required to provide actual pressure and flow data measured at specific fire hydrants within the County’s water distribution system. This data is used in assessing the pressure and flow available for fire protection and in sprinkler system design to ensure public safety. 
  • A SWAMP Request with EDU Worksheet is required for all projects whose projected flows are equal to or greater than 5 Equivalent Dwelling Units (EDUs).
    https://aacoprod.aacounty.org/EDU/loadSwampWorksheet.do 
     
  • A Public Works Agreement (PWA) is a formal legal contract between the developer and the county when public improvements are proposed related to public storm drain, water and sewer, Stormwater management plans, and road plans (including but not limited to pavement marking, signal plans, traffic control improvements).
  • In general- A Public Works Agreement (PWA) is required any time there is work associated with connection to or extension of a public improvement. 
  • For this document- A PWA is required if the connection cannot be completed using a TAP permit (See #8 for tap permit requirements).
  • Please refer to the PWA submittal requirements checklist Public Works Agreement – Submittal Requirements
  • For utility-related improvements, there are generally three types of PWAs. A PWA for a main line extension, one for a proposed individual system, and one when an existing system is impacted by development.  
  • Please refer to Blue Notice IP-22-03 regarding Low Pressure Sewer (LPS) connection requirements IP-22-03 | Anne Arundel County Government
  • After PWA is executed, a pre-construction meeting is required prior to the start of the work.
     
  • A connection can be proposed using a TAP permit if the following conditions are met: 
    • The connection to the main is at a depth less than 18 feet
    • An easement is not required for any part of the service connection UNLESS the easement is already recorded and filed as part of a subdivision. A copy of the recorded easement should be included with the TAP application in this case
    • The connection is not within a State Highway Right-of-Way
    • The proposed connection does not serve more than 3 lots 
    • The water service pipe diameter is 2 inches or less
    • The sewer service pipe diameter is 6 inches or less 
    • The existing water or sewer main is within 75 feet of the connecting property 
       
  • Verify all conditions above are met and then submit TAP application using LUN TAP Permit | Anne Arundel County Government
  • DPW will determine if additional documentation or processes are required during the review of the submittal.