South Shore Trail

South Shore Trail

Directions to South Shore Trail 

 

Brief Project Description

The South Shore Trail primarily utilizes the abandoned road bed of the WB& A Railroad between Annapolis and Odenton. The trail will connect with the Colonial Annapolis Maritime Trail on the east end and the WB & A Trail on the west. The trail will be a component of the East Coast Greenway and the American Discovery Trail. 
 
The South Shore Trail's multi-phase construction will consist of the following:
  • Phase I: Waterbury Road to MD Route 3 (1.97 mile)
  • Phase II: MD Route 3 to Odenton (2.07 mile)
  • Phase III: Bestgate Road to Eisenhower Golf Course (2.59 mile)
  • Phase IV: Eisenhower Golf Course to Waterbury Road (3.55 mile)
  • Phase V: Bestgate Road to City of Annapolis (3.37 mile)
 
  
  

 

Maps and Additional Information

South Shore Trail
 
South Shore Trail
 
South Shore Trail Phase III and Phase IV
 
 

 

 

Schedule

South Shore Trail Phases 
Phase II:Design  (95%) and permitting in process as of Fall 2020.
Phase IV:Feasibility study under review by Bike Commission. Design consultant being sought.
Phase V:May be addressed via DPW/OOT Study to Connect Poplar Trail to South Shore Trail
Phase I:Open
Phase Va:Open

 
 

Status of Other Phases

Phases 
Phase III:Feasibility study conducted with phase IV. Design effort in future years and will connect to phase IV. 
MD 3 Crossing: Feasibility Study is complete. Design and construction is contingent upon future funding.
 
 South Shore Trail
Phase Va - South Shore Trail next to the Annapolis Plaza
 
South Shore Trail
Phase Va - South Shore Trail from behind AAMC (Anne Arundel Medical Center)
 

South Shore Trail Meetings

No Meetings Scheduled