Shipley's Choice Dam Rehabilitation
Project Background: |
The Shipley's Choice Dam is a 20 ft high earthen embankment constructed in 1980 to create an instream stormwater management pond for the Shipley's Choice subdivision. In 2006, an enlarged wet area was discovered on the dam's downstream slope prompting emergency corrective work.Further engineering evaluations determined that long term repairs would not be effective.
|
Benefits: |
|
Project Manager/Contact: |
Larry Mathena
410-222-7908
|
Consultants: |
Johnson, Mirmiran & Thompson, Inc. (JMT)
|
Additional Information: | |
Project Investment: |
$5.4 million
|
Notice to Proceed: |
September 2018
|
Completion Date: |
Fall 2020
|
Project Updates: |
Greater Severna Park Council Presentation - February 2021
Shipley's Choice Construction Schedule (Updated February 2020) Shipley's Choice Project Manual Shipley's Choice Plan Set Latest Project Update Shipley's Choice Project Update - July 2020 |
Related Image: |
![]() |