Project Background:
The Anne Arundel County Department of Public Works has completed a study of the feasibility, potential impacts, and costs associated with the installation of sidewalks along Hillcrest Road, Higgins Drive, Winer Road, Monie Road, Hammond Lane, Greenwood Street, and Holiday Street.  
Benefits:
Identify improvements for pedestrian traffic along these roads.  
Project Manager:
Dan Anderson
410-222-7566
pwande85@aacounty.org
Consultants:
Project Investment:
Notice to Proceed:
Completion Date:
Project Updates:

Project Update for Week of May 22, 2017

 

The study is complete and the Department of Public Works is seeking comments from the potentially affected residents.  Residents are asked to review all the information provided below and comment by July 1, 2017.

Odenton Area Sidewalks Full Report

Odenton Area Sidewalks Drawings

DPW Bureua of Highways Neighborhood Traffic Control Page

 

Comments can be emailed to pwcust00@aacounty.org or mailed to 2662 Riva Road, Suite 400, Annapolis, Maryland 21401.