Broadneck Water Reclamation Facility ENR
Project Background: |
This capital project is one of seven active ENR upgrade projects designed to comply with the State’s Bay Restoration Program pollutant load limits. The wastewater treatment process will be upgraded to state-of-the-art standard known as Enhanced Nurtrient Removal (ENR). When complete, nitrogen concentrate levels will be reduced from 8mg/L to 3 mg/L and phosphorus from 2 m/L to 0.3 mg/L. The current wastewater treatment process was originally designed based on past nutrient removal goals. Upgrades change the existing process and includes:
|
Benefits: |
|
Project Manager: |
Mary Sawitzki
(410)224-1276
pwcust00@aacounty.org
|
Consultants: |
Contractor: Galway Bay Corp.
|
Project Investment: |
$24 Million
|
Notice to Proceed: |
June 2011
|
Completion Date: |
January 2016
|
Project Updates: |
Dec 2013 - Project Underway
|
Related Image(s) |
![]() |