Skip Navigation
 

 

Heritage Complex
2662 Riva Road
Annapolis, MD. 21401
(410) 222-7500

 

 

Department of Public Works - Bureau of Engineering 
  
 

Social Networking Icons (Fb, Twitter, RSS, Pinterest, Email List)

 
 

Mill Creek Sewer Pumping Station Upgrades

Weekly Project Updates

As of August 25, 2014

Site Work
Site work includes underground piping operations. Crews will also install a job site noise reduction fence to minimize impact to surrounding property owners.  The 24-hour by-pass operation will continue until the pumping station is online.  Site work this week includes underground piping along with schedule deliveries.
MondayDiesel fuel delivery
WednesdayDiesel fuel delivery
FridayDiesel fuel delivery
ThursdayTanker truck portable toilet service
Concrete
No deliveries scheduled this week
Building Modifications
None
Electrical
Install underground ductbank
 

Background

The Mill Creek Sewer Pumping Station in Arnold was built in 1970 and currently serves 12,900 properties.  The station is designed to handle 10.8 million gallons of wastewater per day (MGD).  The facility collects wastewater from 44 upstream pumping stations, 147 miles of gravity sewer mains and 31 miles of force mains.  The current average dailly flow is 3 MGD with a peak flow of 7.2 MGD. However, it is designed to handle 10.8 MGD. The facility was upgraded in 1992 with the addition of a third pump.  

Project

Anne Arundel County has invested $9 million to upgrade the Mill Creek Sewer Pumping Station to minimize the amount of sanitary sewer overflows and improve the operations and reliability of the 44-year-old facility.  The mechanical and electrical components and remote monitoring controls will be replaced or upgraded.  Other upgrades are designed to limit the amount of overflows during power outages and the volume of wastewater lost during an overflow.  

Upgrades 

  • All new mechanical and electrical components
Mill Creek Overflow Presentation
Director Chris Phipps Letter to the Editor
MDE Sanitary Sewer Overflow Database
Information
Project ManagerVahid Tayebi
Phone number410-222-7537
ContractorNorair Enigneering
Total Cost$9.6 million
Notice to ProceedApril 2013
Completion (Est) December 2014
 
 
Email DPW Customer Relations

 
  • Expanded wastewater overflow well storage
  • New permanent generator 
  • An independently powered bypass pump

Benefits

  • Improve reliability and operations for facillity.
  • New overflow storage expands current capacity from 21,600 gallons to 175,000 gallons
  • Expanded overflow storage increases time to restore power during outages before spills occur (at avg. daily flow) from current 10 minutes to 1 hour and 24 minutes. 
  • Bypass pump adds fourth level of redundancy. 

Return to Highlighted Capital Projects

 


Anne Arundel County, MD. 44 Calvert Street Annapolis, MD. 21401 | Telephone: (410) 222-7000 | Suggestions | Disclaimer

Copyright 2008; All rights reserved